Technical data of the Henne dam
The barrier structure of the Henne dam is a rockfill dam with a two-layer asphalt concrete outer seal with a drainage layer and a special braking zone to prevent seepage inside the dam. It was one of the first dams with a surface seal made of asphalt concrete. Another special feature is the crown protection structure, a reinforced concrete construction weighing 5,000 tonnes under the crown of the structure.
| Water management | |
| Reservoir capacity | 38.4 millionm3 |
| of which forebay | 0.73 millionm3 |
| Reservoir level above sea level | 323,30 m |
| Catchment area | |
| Henne | 55.15 km2 |
| Diversions | 43.93 km2 |
| Total area | 99.08 km2 |
| Reservoir surface area at reservoir target | 2.10 km2 |
| Barrier structure | Rockfill dam (with surface seal) |
| Greatest height | 60 m |
| Crown length | 376 m |
| Largest base width | 250 m |
| Crown width | 10 m |
| Dam capacity | around 1.3 millionm3 |
| Bottom outlets | |
| 2 steel pipelines with a diameter of 1.5 m laid in two separate tunnels Regulation: Ring piston valves or power station | |
| Max. flow rate per bottom outlet | 26m3/s |
| Spillway | |
| Fixed weir made of reinforced concrete with a crown length of 33 m, horizontally movable gate at the upper end of the spillway, followed by weir channel and energy conversion structure | |
| Max. flow rate | 42m3/s |
| Discharges | |
| Average annual inflow (1961 - 1993) | 23.9 millionm3 |
| Structures: | |
| Diversion of the Brabecke to the Kleine Henne: | |
| Tunnel length | 2.5 km |
| Clearance height | 2,13 m |
| Clear width | 1,76 m |
| Stream development "Kleine Henne" | 3.2 km |
| Diversion of the "Kleine Henne" to the Horbach: | |
| Tunnel length | 1.8 km |
| Clearance height | 2,26 m |
| Clear width | 1,96 m |
| Horbach" creek development | 2.3 km |
| Mielinghausen forebay with a forebay dam | |
| Dam height above sea level | 323,30 m |
| Dam height above the valley floor | 12 m |
| Dam height above the rock base | 17 m |
| Crown width | 10 m |
| Crown length | 175 m |
| Largest base width | 62 m |
| Bulk masses | around 50,000 m³ |
| Sealing through internal stone scaffold clay body | |
| The hydropower plant has an output of 2.0 MW and supplies an average of 5.8 GWh of electricity per year. It is operated by Lister- und Lennekraftwerke GmbH, a wholly owned subsidiary of the Ruhrverband. | |
| Power stations | |
| Supply lines through the left bottom outlet with a diameter of | 1,5 m |
| Branch lines to the turbines with a diameter of | 0.8 m and 0.5 m respectively |
| 2 machine sets: | |
| Effective gradient | 56 m |
| Set 1 | |
| Siphoning capacity | 3.6m3/s |
| Capacity | 1,400 kW |
| Set 2 | |
| Capacity | 1.6m3/s |
| Capacity | 600 kW |